New Foxborough
Public Safety Facility
 

 

 

 

 

 

 

 

 

 


The Foxborough Police and Fire Departments want to express our thanks to the voters
of Foxborough for their support in voting to fund our new Public Safety Facility

 

We will be posting photographs and information about the facility here as work progresses

 

Once again, thank-you for your support

 

 

 

PROJECT UPDATES

 

October 1, 2004

 

Building Architect Chosen

 

After an extensive search, the Permanent Building Committee has chosen the firm of Kaestle Boos Associates to design the new facility.  Kaestle Boos is a nationally recognized consulting firm specializing in the design of Public Safety Facilities.  They have worked with over 60 public safety agencies and become a leading service provider for this specialized building type.  The firm recently completed the new North Attleborough police facility.  To see some Kaestle Boos projects :  http://www.kba-architects.com

 

 

November 17, 2004

 

Site Work Begins

 

Contractors have begun site preparation work.  The work will include the demolition of the buildings currently on the site.  The contractor hopes to have the demolition completed by mid January 2005.

 

May 3, 2006

 

Ground Breaking

 

 

Ground breaking ceremonies were held on Wednesday, May 3, 2006.  Bilt Rite Construction of Boston has begun work at the site.  Over the next few weeks workers will be preparing the site for the pouring of the building footings and foundation.

 

 

 

PHOTOGRAPHS 

 

 

 


Click on thumbnail for larger picture

Site of new Public Safety Facility, September 2004

Former State Hospital building, September 2004

Former State Hospital building, September 2004

Building demolition begins, Jan 10, 2005

Building demolition begins, Jan 10, 2005

Demolition Continues,
Jan 22, 2005

Interior view, Jan 25, 2005

Demolition nears completion, Jan 25,2005

Ground breaking ceremony
May 3, 2006

Site preparation work
May 4, 2006

Site preparation work
May 4, 2006

Site preparation work
May 4, 2006

Site preparation work
May 4, 2006

Footings and Foundations
June 15, 2006

Footings and Foundations
June 15, 2006

Steel erection begins
July 27, 2006

Steel erection begins
July 27, 2006

Steel erection progress
August 13, 2006

Steel erection progress
August 13, 2006

Block wall construction and floor slab poured
September 11, 2006


Block wall construction and floor slab poured
September 11, 2006

Building view – rear side
September 11, 2006

Construction Progress
November 11, 2006

Construction Progress
November 11, 2006


Construction Progress
November 11, 2006

Construction Progress
November 11, 2006

Roof & Truss work
December 7, 2006

Roof & Truss work
December 7, 2006

Construction Progress
January 24, 2007

Construction Progress
January 24, 2007

Construction Progress
January 24, 2007

Construction Progress
January 24, 2007

Construction Progress
January 24, 2007

Lobby Area
April 24, 2007

Male Locker Room
April 24, 2007

Training/Meeting Room
April 24, 2007

Construction Progress
April 24, 2007

Parking Area Graded
April 24, 2007

Parking Area
May 22, 2007